This plastic machine installation checklist is the one we send to buyers while their machine is still at sea. The machine itself is usually the easy part. What delays start-up is the factory around it: a main switch that is too small, compressed air at the wrong pressure, a chiller that cannot hold mould temperature in summer, or no crane to lift the clamping unit off the truck. Every one of those can be fixed in advance, cheaply, and almost none of them can be fixed quickly once the technician is standing in your hall.

The checklist applies to injection moulding machines, PET blow moulding machines, extrusion blow moulding and most other plastic processing equipment. Always follow the manufacturer's foundation drawing and utility data sheet for your specific model; this guide tells you what to ask for and what to check.

Why preparation decides your start-up date

A commissioning technician typically comes for a fixed number of days. If the factory is ready, those days go into setting up the mould, tuning the process and training operators. If it is not, they go into waiting for an electrician, and you either pay for extra days or the technician leaves before your operators are confident. Ask your supplier, or HassanPlas if we are handling your project, for the utility requirements sheet as soon as the contract is signed. It should state:

Floor, foundation and ceiling height

Most small and medium injection and blow moulding machines stand on a sound, level industrial concrete floor using anti-vibration levelling mounts, without a special foundation. Large machines, high-speed machines and long extrusion lines may need a dedicated reinforced pad, sometimes isolated from the surrounding slab. The manufacturer's drawing is the authority.

HassanPlas tip: Mark the machine outline, including the mould area, safety gates and maintenance access, on the floor with paint before the container arrives. It immediately shows whether the space really works.

Unloading and moving the machine

Decide in advance how each crate will come off the truck and onto its final position. Check the packing list for the heaviest piece.

Power supply sizing

Electrical supply is the most common cause of delayed start-up. Work with a qualified electrician using the machine's data sheet.

Main switch and cable

For a three-phase load, current is roughly the power divided by (1.732 × voltage × power factor). As a worked example, a machine drawing 100 kW at 400V with a power factor of 0.85 draws about 170 A at full load. The electrician then selects a main breaker and cable cross-section with appropriate margin for that current, the cable length, the installation method and the local electrical code. Remember to add the auxiliary equipment: chiller, dryer, loader, compressor, mould temperature controller and conveyors often add a significant share to the line's total load.

Voltage and frequency

Confirm the machine was built for your supply: for example 380V/50Hz, 400V or 415V/50Hz, or a 60Hz supply such as 220V, 440V or 480V. If it was not, a transformer may be needed. Check the nameplates on arrival.

Voltage stability

Where grid voltage fluctuates or drops under load, controllers, servo drives and heaters suffer. Measure your supply at different times of day before installation. Depending on the readings, you may need a voltage stabiliser, a dedicated transformer, or power-factor correction. If you rely on a generator, size it for the starting current of motors and compressors, not only running load.

Compressed air: low pressure and high pressure

Compressed air requirements vary more between machine types than any other utility, and confusing them is a classic mistake.

Machine typeTypical air pressureWhat it is used forNotes
Injection mouldingLow pressure, typically 6–8 barMould blow-off, air valves, robots, pneumatic gatesConsumption usually modest; check robot and mould requirements
Extrusion blow mouldingLow pressure, typically 6–10 barParison blowing, pneumatic movementsLarger containers and multi-cavity heads use more air
PET stretch blow mouldingHigh pressure, commonly 25–40 bar for blowingPre-blow and final blowing of bottlesNeeds a high-pressure compressor plus a separate low-pressure supply for actuators
Injection blow mouldingLow to medium pressure; check data sheetBlowing and actuatorsConsumption depends on cavities and container size

For PET lines in particular, size the high-pressure compressor on the machine's stated consumption at full output, plus a margin, and plan for future cavity increases. A complete compressed air system should include:

Common mistake: Buying a PET stretch blow moulding machine and assuming the factory's existing 8-bar compressor will do. It will not. The high-pressure compressor is a separate, significant purchase and should be in the budget from day one.

Cooling water, chillers and cooling towers

Cooling determines cycle time. An undersized chiller shows up in hot months as longer cycles, warped parts and hydraulic oil overheating.

Chillers, cooling towers and mould temperature controllers are all available through our auxiliary equipment range, sized to match the main machine.

Air-cooled industrial chiller for plastic moulding machines
An air-cooled chiller is the simplest option for mould cooling where a cooling tower is not available.

Material handling and ventilation

Most plastics need some combination of drying, conveying and mixing before they reach the barrel.

Moulding halls get hot from heaters, motors and hydraulic systems. Plan for ventilation or extraction above the machines, and keep the area around chillers and electrical cabinets within their rated ambient temperature. Very high ambient temperatures reduce chiller capacity and shorten electronics life.

Layout, flow and safety

Lay out the line in the order material flows: raw material storage, drying and conveying, the machine, downstream equipment (conveyor, robot, leak tester, packing), then finished goods. Avoid crossing routes for forklifts and people.

Plastic machine installation checklist for technician arrival

Confirm every item below before the technician travels. Send photos to your supplier as evidence.

ItemReady when
Machine and auxiliaries positionedUnpacked, on final position, roughly levelled
PowerCorrect voltage measured, cable terminated at the cabinet, breaker sized and labelled
Compressed airCorrect pressure at the machine, dryer and filters running
Cooling waterChiller and tower running, lines flushed, flow confirmed
Hydraulic oilCorrect grade and quantity on site, per manual
Raw materialEnough for trials, already dried where needed
Mould and preformsOn site, cleaned, with any inserts and spares
Lifting equipmentCrane or hoist available for mould mounting
ToolsBasic hand tools, multimeter, spirit level, torque wrench
PeopleElectrician, maintenance fitter and operators assigned for the full visit
Technician logisticsVisa, accommodation, transport and interpreter if needed

Installation timeline, training and spare parts

A realistic sequence for a single machine with its auxiliaries looks like this, though timings vary with machine size and complexity:

  1. While the machine is in production: receive the utility sheet and foundation drawing; order compressor, chiller and electrical work; pour any foundation.
  2. While at sea: complete electrical, air and water installation; arrange unloading; apply for technician visa.
  3. Arrival: unload, position, unpack, inspect for transit damage against the packing list.
  4. Commissioning: levelling, connections, oil filling, dry running, mould mounting, first shots or bottles, process tuning.
  5. Production trial and training: continuous running at target output, with operators running the machine under supervision.
  6. Handover: written settings, maintenance schedule and sign-off against the acceptance criteria.

Training should cover daily operation, start-up and shutdown, mould change, basic troubleshooting, and preventive maintenance for both operators and maintenance staff. Ask for settings records and photographs so knowledge does not leave with one operator.

Spare parts starter kit

Keep a starter kit on the shelf from day one. Typical items include heater bands, thermocouples, fuses, relays and contactors, proximity switches, seals and O-rings, solenoid valve coils, filters and, for PET lines, blowing valve seals and lamp sets. Ask for a recommended list for your model. HassanPlas dispatches further spare parts from China when needed.

If you are planning a complete new plant rather than a single machine, our guide to starting a PET bottle manufacturing plant covers the wider planning. For installation, commissioning and operator training by technicians, see our services.

Frequently asked questions

Does an injection moulding machine need a special foundation?

Most small and medium injection moulding machines stand on a level, sound industrial concrete floor using levelling mounts. Large or high-speed machines may need a dedicated reinforced foundation. Always follow the manufacturer's foundation drawing for your model.

What air pressure does a PET blow moulding machine need?

PET stretch blow moulding typically needs high-pressure air, commonly in the 25 to 40 bar range, for blowing, plus a separate low-pressure supply for actuators. Check the exact pressure and consumption on your machine's data sheet and size the compressor, receiver, dryer and filters to suit.

How do I size a chiller for a plastic moulding machine?

Use the cooling load stated by the machine and mould supplier, add a margin for your hottest ambient temperature and for future moulds, and choose between air-cooled and water-cooled designs based on your site. Undersizing shows up as longer cycles in hot months.

How do I size the main breaker and cable?

Add up the installed power of the machine and all auxiliaries, calculate full-load current for your voltage, and have a qualified electrician select the breaker and cable cross-section according to cable length, installation method and local electrical code.

Do I need a voltage stabiliser?

If your supply voltage fluctuates or drops under load, a stabiliser or dedicated transformer protects controllers, servo drives and heaters. Measure the supply at different times of day before installation to decide.

What should be ready before the commissioning technician arrives?

The machine positioned, power connected at the correct voltage, compressed air and cooling water running, hydraulic oil, dried raw material, the mould, lifting equipment, basic tools, and an electrician, fitter and operators assigned for the whole visit.